03 / BUDGET PLANNER

Start with a range. Price the rest locally.

Use a published Philippine covered-court estimate to size the roofed area, then record your own allowances for work the benchmark excludes or does not clearly cover. Every amount here is in Philippine pesos.

For one covered public-use court in Cebu Province. The lot, local municipality, soil, drainage, wind exposure, access, and final scope still need professional review and written quotes.

CALCULATE THE ROOF BENCHMARK

Change a size or finish tier.

Set the roofed area

The default 38 × 68 ft (11.58 × 20.73 m) roof is an illustrative allowance around the preferred clear playing area. Your survey and design team must confirm the real roof.

Positive width in feet.
Positive length in feet.
Choose a published finish tier

These AEDO 2026 Philippine planning bands apply per square meter of roofed area; their included scope must be checked in a local quote.

Enter separate owner allowances

Optional entries in PHP. Leave a field empty when it has not been priced. A typed 0 is recorded as your ₱0 estimate. Ask local contractors for actual scope and prices.

Blank means not priced yet; 0 means your ₱0 estimate.
Blank means not priced yet; 0 means your ₱0 estimate.
Blank means not priced yet; 0 means your ₱0 estimate.
Blank means not priced yet; 0 means your ₱0 estimate.
Blank means not priced yet; 0 means your ₱0 estimate.
Blank means not priced yet; 0 means your ₱0 estimate.
Blank means not priced yet; 0 means your ₱0 estimate.

PUBLISHED ESTIMATE · AEDO ENGINEERING 2026

Your roof-area benchmark

38 × 68 ft (11.58 × 20.73 m) · 240.1 m²

Standard finish · ₱12,000–₱19,000 per m²

₱2,880,737–₱4,561,168

Published Philippine planning range for roofed area. This is not an official Cebu price or contractor bid.

Owner allowances, kept separate

Sitework and drainage
Not priced yet
High ball-containment fence and gates
Not priced yet
Permanent net and posts
Not priced yet
Lighting beyond benchmark scope
Not priced yet
Separate amenities and accessible facilities
Not priced yet
Professional design and permits
Not priced yet
Utility connections
Not priced yet

Planning subtotal withheld until all seven allowances have a value. Blank means not priced yet; enter 0 only if you intend a ₱0 owner estimate.

Still not a full build bid

AEDO Engineering third-party Philippine planning range; owner allowances are separate estimates. Confirm complete scope and local prices with Cebu professionals and contractors.

AEDO excludes or does not establish pricing for:

  • Land purchase or lease
  • Site development, including difficult ground, fill, retaining, and drainage work
  • Separate ancillary buildings and amenities
  • Court equipment, including a permanent outdoor net and posts
  • Professional design and fees
  • The proposed high ball-containment fence and gates are not assumed in the benchmark

The quoted band does not establish that this concept’s tall ball-containment fence is included. Verify any overlap between the selected finish tier and your allowance lines in each written local quote.

EXAMPLE / 38 × 68 ft (11.58 × 20.73 m) ROOF

The published bands at about 240.1 m².

These rounded examples use the same roof-area calculation as the planner. They cover the benchmark only, before any separate owner allowance.

Basic

~₱1.92M–₱3.12M

Published estimate · ₱8,000–₱13,000/m²

Standard

~₱2.88M–₱4.56M

Published estimate · ₱12,000–₱19,000/m²

Premium

~₱4.32M–₱6.96M

Published estimate · ₱18,000–₱29,000/m²

SUPPLIER LISTING EXAMPLES

Equipment needs its own quote.

PickleballPH listed portable nets at ₱5,950 and ₱29,500 in the 2026-09-25 research snapshot. These are listings, not installed permanent outdoor systems. Check freight and exact outdoor suitability; request a local price for permanent posts, net, and installation.

OPERATING PRICE COMPARATOR

A Cebu playing-fee example.

SunStar Cebu reported ₱150 for weekday daytime play and ₱250 for weekend or night play at a Liloan venue. This is one reported customer price, not a construction price or revenue projection.

Take the numbers into a scope conversation.

Ask each contractor which court surface, roof, drainage, fence, lighting, electrical work, and public amenities are in their price. Keep every exclusion visible in the written proposal.

Read the build sequence